This weekend was all about doing odd jobs to get ready for the frame inspection next weekend.
– Add in any missing blocking in the walls
– Add in blocking in the ground floor between the ceiling joists
– Make sure all the uni-ties holding the main rafters to the beams and dwarf walls all have 4 nails in them on each end. Add in any missing brackets
I also finished the ceiling joists under the hot water service tank.
I added all the plywood baffles on the dwarf walls between the rafters as air barriers and as backing for the spray foam.